Calendar

Project Status

  • All Construction and procurement activities are
    on schedule & on budget
  • 25 km of service and access roads completed
  • 44 foundations completed
  • Permanent 80M met tower installed fall 2007
  • Balance Of Plant (BOP) is approx. 95% complete
  • Main transformer delivered to site
  • First shipment of 9 complete units completed

Project Schedule

Environmental assessment Jan. 06 to Feb. 07
Electrical interconnection assessment In progress
Begin detailed engineering June 2006
Begin construction of access roads May 2007
Begin installation of wind turbines April 2008
Start up and commissioning June-September 2008
Commercial operation October 2008

Stages of a Wind Farm

Prospecting (Approximately 1 year)
  • Business plan
  • Mapping of winds
  • Strategic studies
  • Legal and regulatory framework
  • Analysis of constraints
  • Meetings with property-owners
  • Preliminary feasibility studies

Development (From 1 to 2 years)
  • Installation of wind measurement masts
  • Advanced meteorology
  • Evaluation of wind energy potential

Engineering studies (From 1 to 2 years)
  • Studies of impact on the environment, wildlife, plant life, the countryside and noise
  • Public consultations
  • Geological studies
  • Network integration studies
  • Agreement with property-owners
  • Order equipment, agreements with contractors
  • Permit applications

Construction (From 1 to 2 years)
  • Performance tests
  • Construction of access roads
  • Construction of foundations
  • Erection of the towers
  • Installation of electrical equipment, transformer station and cables
  • Testing and start-up

Operation (From 20 to 25 years)
  • Maintenance of the wind farm